2008 HEAVY CommErcial
Runner Up
Sun Valley Comunity Church
Project Statistics
Location: Gilbert, Ariz.
Type: Church, mezzanine, and classrooms
Size: 84,000 sq. ft. (floor)
ICF Use: 52,000 sq. ft. (walls)
Height: 34 feet, reaching 50’ high on mezzanine
ICF System: 8” core, Arxx
Project Timeline
Total Construction: 300 days (Oct 2006 to Nov. 2007)
ICF Start-to-Finish Time: Approx. 6 months
Fast Facts
- ICFs chosen for sound attenuation, fire rating, and fast installation.
- ICFs used for decorative columns and beams in front structure
- Distributor and ICF Manufacturer educated architect and engineer
- Creates quiet, comfortable sanctuary for pari-shoners
- ICF walls allows for multiple uses without disrupting others
|