2011 Light Commercial
2nd Runner Up
Buckeye Valley Fire Station
Project Statistics
Location: Buckeye, Arizona
Type: Fire Station
Size: 18,000 sq. ft. (floor)
ICF Use: 10,600 sq. ft. (all exterior walls) plus 1,000 sq. ft. interior walls
Cost: $4 million
Total Construction: 142 days
ICF Start-to-Finish Time: 45 days
Construction Team
Owner: Buckeye Valley Fire District
General Contractor: Core Construction
ICF Installer: Sun Valley Masonry
Architect: Perlman Architects
ICF System: eForm by Reward
Fast Facts
- LEED Gold Certification
- SIP roof with R-54 rigid foam insulation
- 41% more efficient than ASHRAE standards
- Tall-wall construction
- Multiple wall finishes easily attached to ICF
- Numerous corners
- Completed $200,000 under budget and three weeks early
- Open house educated community about ICF technology
|