EPS decking systems, like the Lite-Deck used on this New England resort project, are a great match for commercial ICF jobs. For more on this project, see the profile on p.20.

With most commercial ICF jobs, wooden floor joists are not the best option. Often the spans, fire codes, and weight loads just won’t allow it. On other projects, sustainability concerns, like energy efficiency and life cycle costs, are driving factors. A number of excellent alternatives exist, all of which work extremely well with ICF construction.

One popular solution is to use prefabricated steel joists. 

FloorSPAN by Metwood and Hambro by CanAm Steel Corporation offer longer clear spans with less joist depth. Openings in the joists make wiring, plumbing and HVAC a cinch, and the joists themselves can be installed by carpenters, saving on labor costs.

“It just makes for a much better building,” says Barry Gow, a Hambro representative based in Ontario, Canada. Gow supplied the joists for a 230,000 sq. ft., 5- story apartment complex in Halifax. (See project profile on p. 18)

Peter Polley, who oversaw the development project explains, “The typical unit involves two bathrooms and a washer/dryer in each of the 64 units. There is such an incredible amount of ducting. If you use regular concrete flooring, you’d have a 7-foot ceiling in half the unit, or have to go to a 9 foot ceiling throughout the building. Hambro gives us the ability to do all the mechanical work within the joist space.” The joists support a concrete slab 3 inches thick.

Polley also used Hambro joists in the Villas at Mont Blanc, which earned Best Residential Development from the ICF Builder Awards in 2005. The Villas feature an in-floor radiant heat system, powered by electric boilers, which allows residents to capitalize on a Nova Scotia program that sells power during off-peak hours at a 30% to 50% discount. 

FloorSPAN by Metwood offers similar advantages. “It’s a structural steel I-beam with the utility holes pre-cut in it,” explains Mike Callahan, owner of Metwood. 

“There are advantages for Metwood beams in just about any application, but especially those that involve concrete floors,” he says.

Coupled with metal pan decking and a concrete floor system, the beams are incredibly strong. “Joists can be placed up to 8 ft apart, and still be strong enough to park cars on,” says Callahan. “When you’re placing the slab, Metwood can span up to 32 feet without any additional shoring required.”

There are other advantages as well. “Any carpenter familiar with light gauge steel studs can install our product. The GC doesn’t need to go to a steel erector because there’s no welding at the jobsite.”

“It installs as fast as anything, and you don’t have to tear anything out,” continues Callahan. “If you do have to use shoring, it’s minimal.” 

Steel decking is another great option for commercial ICF work. Often, all the mechanical and HVAC work will fit into the plenary space created by the joists.

Like Hambro, saving on the depth of the floor joists translates

to savings throughout construction. “
If you save one course of block and three or four courses of brick on every floor of a four story hotel, that adds up,” he says. “It doesn’t take long to realize that this can be a better buy.”

Another effective material for commercial ICF construction is EPS decking. It offers all the advantages of precast, with the additional benefits of being cheaper to ship and easier to finish.

Dave Hall, marketing director at Lite-Form Technologies, which invented Lite-Deck, says, “Transportation costs are a huge thing. With Lite-Deck, you don’t have to haul concrete panels to the jobsite. Foam is not only cheaper to ship, but it’s cheaper to make as well. Plus, you get the quality control of site-cast work.

The product consists of EPS foam planks, which are delivered to the jobsite custom-cut to length. Workers simple lay them out, install shoring and rebar, and then pour. Combined with post-tensioned cables, clear spans of more than 40 feet can be achieved.

Lite-Deck, and similar products such as Insuldeck and AmDeck, are a great option for jobs that require a complete concrete building envelope. A school district in central Oklahoma, for instance, used Lite-Deck to create a tornado-proof roof on two ICF schools in town. (See story on p. 16).

Others use the product with radiant heat flooring. “You’re getting the insulation without any extra work,” explains Hall. Developers of a time-share resort in New England chose Lite-Deck for flooring precisely for that reason. (See story on p. 20).

“We wanted our guests to have the very best,” says Tom Behrens, owner of Mountain Edge Resort. “That meant using ICFs on all exterior and interior demising walls, as well as using foam in the ceiling and floor assemblies.” The result is that each unit is extremely energy efficient and virtually soundproof.

With Lite-Deck, finishwork is simple. Utility chases can easily be cut into the foam using a hot knife or Sawzall. Drywall or other finishes are fastened to the metal furring strips. Hall says Lite-Form can precut the chases for you if desired. 

Mountain Edge Resort used foam decking to provide guests with unmatched quiet, thermal comfort, and luxury. “We wanted our guests to have the very best,” says Tom Behrens, owner of the resort. See story on opposite page for more.

Note that while Lite-Deck can accommodate electrical work, HVAC and other mechanical ducting will not fit in the joist space, as it would with steel joists.

As the commercial ICF market continues to grow, the demand for longer spans, better flooring materials, and more sustainable building practices will increase as well. Steel floor joists and EPS decking are viable solutions to these building challenges. Especially with ICF construction, wood and precast concrete are no longer the only options. 

Residences At Mont Blanc

The Residences at Mont Blanc consists of two 64-unit, 5-story apartment buildings beautifully situated over Halifax Harbour.

With their multi-faceted façade of bay windows and striking red roofs, the buildings have become a community landmark and helped revitalize the entire area.

The building site, despite the outstanding views, had remained vacant for many years. Originally, it held a number of large fuel oil tanks, but soil contamination and noise gave most developers the impression that the site was unbuildable. 

Peter Polley, president of Polycorp Developments, thought otherwise. “The site was challenging in that all the native till had to be removed and replaced with structural fill prior to construction,” he says. “Also the site was accessible from only one side, which meant that onsite staging had to be erected to provide adequate support for the concrete pump truck.”

Lastly, there was a tremendous amount of noise. The port, which operates 24 hours a day, was less than 150 yards away. A major highway and rail line ran between the port and the building site, and traffic on a nearby major bridge contributed as well. “We knew that if we didn’t do something about the noise, the buildings would be largely uninhabitable,” he says.

ICF construction helped resolved nearly all these problems. They chose Arxx, which have an STC rating of 50+. Polley says that the combination of foam and concrete nearly eliminates the outside noise completely. “The units are incredibly quiet,” he says. “It has allowed us to charge premium rents just 400 feet from a major port facility and rail line. If we didn’t have ICF walls we would have serious vacancy and turnover problems, but we’ve been very successful renting the units and keeping the building full.” 

ICFs also helped speed construction. Each building has 82 corners, which would normally add significantly to a project’s cost. Careful design work, however, made it easy.

“All of the corners and walls are laid out to the exact dimensions of the block,” explains Polley, “so even though we had so many corners, there was no cutting and no waste. Window and door sizes were also selected to
minimize waste.” 

Polley used steel joists from Hambro for the floors. The open web design allowed builders to put all the mechanical components in the joist space.

Arxx walls insulate as well as an R-50 frame wall, which is important during the long harsh winters. “I estimate these units are at least 20% more efficient that any other complex in the city,” says Polley, “despite the fact that they have more windows. Fully one-third of the exterior is glass, but tenants still have abnormally low energy bills.”

Polycorp is already working on their next project, a seven-story condo, also built from Arxx ICFs. Polley reports the building is 80% sold and the exterior walls aren’t yet completed. 

n

Construction Team

Developer: Polycorp Developments, Inc.
Architect: Michael Napier Architecture
General Contractor: Polycorp Developments, Inc.
ICF Installer: Polycorp Developments, Inc.

l

Fast Facts

Location: Halifax, Nova Scotia
Size: 230,000 sq. ft
ICF Walls: 130,000 sq. ft
Cost: $16 million
Completed: 2006
ICF Form: Arxx
Floor System: Hambro

Mountain Edge Resort, Sunapee, New Hampshire   

As the largest and nicest condominium complex in the region, Mountain Edge Resort caters to a discriminating clientele, which is just one reason owner/developer Tom Behrens chose to build with ICFs. He had used IntegraSpec ICFs on several other projects, so he knew which brand and contractor he was going to work with early on. 

He also insisted on using Lite-Deck for the floors.

“We like the R-Value, and it works very nicely with IntegraSpec,” says Tammy Gaherty, a sales representative at the resort. “Having the soundproof rooms, the high R-Value, and having a healthier environment are now some of the selling points used when we market the resort and spa.”

The lower level was constructed with 8” and 10” concrete cores to offset the 10’ of backfill pressure. Cretepavers installed 6” and 8” concrete cores for the above grade exterior and interior demising walls. 

l

Fast Facts

Location: Newbury, New Hampshire
Size: 82,000 sq. ft.
Completed: Oct. 2004
Outstanding Energy Efficiency and Disaster Resistance

n

Construction Team

Owner:Mountain Edge Resorts
General Contractor: Mountain Edge Resorts
ICF Installer:Cretepavers, Inc.
Distributor:Cretepavers, Inc.
Form:IntegraSpec
Flooring:Lite-Deck

Vernon View Luxury Condos,  Huntsville, Ontario 


Norm Goodfellow believes in quality. That’s why he only uses ICFs for the high-end condos he is developing in the rolling hills of Muskoka.

“We only build one condo per year,” he says, “but we do everything from developing the land to stacking the ICFs to marketing the units. We make sure everything is the very best.” The first two projects were built with Amvic, but Goodfellow has used NUDURA brand ICFs for the last two.

“At the height of construction, we were completing a floor every 8 days,” says Goodfellow. The 5-story building has 36 1-, 2-, and 3-bedroom units. Interior walls are steel stud.

Floors were made using Hambro steel joists. “We’ve always used the system, and it works really well,” says Goodfellow. The building is heated using forced air; by using a 16” joist, designers were able to get all the ductwork into the joist space so occupants have no unsightly “bulkheads” on the ceiling. 

l

Fast Facts

Location: Huntsville, Ontario
Size: 60,000 sq. ft.
Completed: 2006
Outstanding Energy Efficiency and Disaster Resistance

n

Construction Team

Owner: Goodfellow Construction
General Contractor: Goodfellow Construction
ICF Installer: Goodfellow Construction
Distributor:Fast Form
Form:NUDURA
Flooring:Hambro