2008 Heavy Commercial
runner Up
Project Statistics
Location: Gilbert, Ariz.
Type: Church, Mezzanine, and Classrooms
Size: 84,000 sq. ft. (floor)
ICF Use: 52,000 sq. ft. (walls)
Height: 34 feet, reaching 50’ high on mezzanine
ICF System: Walls by Arxx; Bracing by Uniscaffold
ICF Installer: Advanced Building Technologies
Total Construction: 300 days (Oct. ‘06 to Nov. ‘07)
ICF Start-to-Finish Time: Approx. 6 months
Fast Facts
• ICFs chosen for sound attenuation, fire rating, and fast installation
• ICFs used for decorative columns and beams in front structure
• Distributor and ICF Manufacturer educated architect and engineer
• Creates quiet, comfortable sanctuary for parishoners
• ICF walls allows for multiple uses without disrupting others