2010 Small Residential
1st Runner-Up

The construction difficulties faced by Joseph Voitehovich in building his dream home would have discouraged a lesser man.  The lot, located at the end of a cul-de-sac, dropped away so steeply that  was considered unbuildable for more than 40 years.

Voitehovich, who immigrated from Russia 20 years ago, is an internationally recognized architect, perhaps best known for designing the Salt Lake City (Utah) Library.  And this home, designed as a work of art, is the culmination of ten years of work.

It would all but eliminate right angles. The back of the house, which doubles a retaining wall, is bent precisely five degrees at its midpoint.  No two walls lie in a parallel plane, so many corners were either 84 or 96 degrees.  Nine corners had to be custom cut. One 84 degree corner went up 31 courses to a final height of 41 feet.

Ceilings were not to be tied into the walls, but float six inches away from the finished interior surface.  Other exterior walls are separated from each other on
the sides and top, creating extreme engineering challenges. Additionally, the owner insisted that the walls be within 1/8” of plumb at all points.

The angles of the roof overhang and deck were calculated
to take maximum advantage of winter solar gain and summer shading.  Radiant heat in the concrete floor is combined with a concrete/EPS decking system to maximize efficiency and reinforce the unusual design.

Dan McCullough, a Utah-based Logix distributor who supplied the ICFs, served as general contractor and ICF installer on the job after several others balked at the project’s complexity.

The thermal mass provided by the Fortruss ICF Floor systems coupled with the energy efficiency of radiant heat were made for each other.

“He wanted to create a home that was not only exceptional in design, beauty and strength but was also very energy efficient,” explains McCullough “ICFs were the only option that met his requirements and budget.”

Working with six different engineering agencies, McCullough finally got the plans approved and began work.  “We had originally planned on starting construction in spring,” he says, “but we ended building right through the worst time of the year. We had to shovel snow every morning.”

Working under tight deadlines set by the financing agency, McCullough and his crew worked 12-hour days to get the foundation up and backfilled.  Much of the work was done using headlamps in the short winter days.

Midway through the excavation, it was determined that the foundation would have to be nine feet deeper than previously thought in order to reach stable soils.  This in turn, made it impossible for the excavator to get off the lower part of the lot. “He had literally dug himself into a hole,” says McCullough. “Our solution was to stack and pour the walls in a stair-step manner so the excavator could backfill against the foundation and create a ramp to get out.

The extreme slope of the lot, unstable soils, and floating walls meant the job would require a lot of steel and a lot of concrete.  “For the majority of the house we used  two  #5 bars 8” on center both vertical and horizontal,” McCullough says.  It ended up with about 58,000 linear feet of rebar and 262 yards of concrete placed in 15 different pours.

ICFs were used for exterior and interior walls, embankment reinforcement, parapets, foundations for the bridge into the garage, even a lawn bench and pedestal for the air conditioning unit.  In all, the job used just under 1,500 ICF blocks.

Voitehovich attentively monitored the entire process. “The fact that Joseph was the customer and architect on this job added a huge responsibility for me,” says McCullough.  “He was on the jobsite at least two to three times a day, usually early in the morning before his workday began, then again at noon and again after work.  He insisted we wait for him to arrive every morning before going over the day’s work. He made changes to the plans almost daily, and every morning he would leave a new set of plans for us at the jobsite. He was there for every pour and every major activity in the construction process.”

By all accounts, McCullough did an outstanding job.  When the house was finished, Voitehovich held not one, but three different open houses: one for his family, friends and neighbors, a second for his fellow architects and co-workers in his office, and a third for the local AIA members.  At each of these, the Logix ICFs and Fortruss EPS Floor were prominently mentioned.  It was featured in the local TV show “Utah Homes.”

McCullough adds, “I get asked all the time about this job and am proud to be associated with the ICF home being built overlooking the city.”

Project Statistics


Location: Bountiful, Utah
Type: Private Residence–Custom Home
Size: 2,980 sq. ft.
ICF Use: 6,660 sq. ft. (All exterior walls) plus 1,300 sq. ft. of interior wall and 2,200 retaining walls.
Additional 3,000 sq. ft. of EPS decking.
Cost: $475,000
Total Construction: 210 (finished June 2010)
ICF Installation time: 100 days

Construction Team


Owner/Architect: Joseph Voitehovich
Engineer: RCB Engineering
General Contractor: McCullough Construction
ICF Installer/Distributor: Utah ICF
ICF System: Walls by Logix/Bracing by Reechcraft/Blockouts by V-Buck

0 Comments

Submit a Comment

Your email address will not be published. Required fields are marked *

Like what you read?

Yearly Subscriptions Starting @ $30