2018 Heavy Commercial (Education)
Best in Class

Project Statistics


Location: Lexington, Kentucky
Type: High School
Size: 287,125 sq. ft. (floor)
ICF Use: 100,000 sq. ft.
Cost: $63 million
Total Construction: 104 weeks
ICF Installation Time: 150 days

 

Construction Team


Owner: Fayette County Schools
General Contractor: D. W. Wilburn
ICF Installer: Gravesco
Form Distributor: Wells Group
Architect: Tate Hill Jacobs
ICF System: Logix ICF

Fast Facts


36’ gymnasium wall with a gable
ICF enabled winter construction
Designed for Net Zero
Local media coverage throughout construction

 

 