2020 Light Commercial
Winner

Project Statistics 


Location: Warner, Hew Hampshire
Type: Fire Station
Size: 11,000 sq. ft. (floor)
ICF Use: 12,000 sq. ft. 
Cost: 2.75 million
Total Construction: 38 weeks
ICF Installation Time: 27 days

Construction Team 


Owner: Town of Warner
General Contractor: North Branch Construction
ICF Installer: Groen Construction
Form Distributor: Atlantic Builders Supply
Architect: SMP Architects
ICF System: Nudura

Fast Facts 


Designed as Emergency Operations Center
43 Wall Openings (Doors and Windows)
4 Corners and 4 T-Walls

0 Comments

Submit a Comment

Your email address will not be published. Required fields are marked *

Like what you read?

Yearly Subscriptions Starting @ $30