2023 Education
2nd Runner-Up

Project Statistics 


Location: Santa Rosa Beach, Florida

Type: Elementary school

Size: 150,000 sq. ft.

ICF Use: 68,000 sq. ft.

Cost: $36,100,000

Total Construction: 70 weeks

ICF Installation Time: 120 days

Construction Team 


Owner: Walton County School District

General Contractor: Childers Construction Co.

ICF Installer: PCS

Form Distributor: Nudura

Architect: DAG Architects Inc.

ICF System: Nudura

Fast Facts


  • The district’s first new school in 20 years and first ICF project
  • Media center, state-of-the-art labs, and outdoor courtyards
  • Uses 50% less electricity than other similar non-ICF schools
  • Building’s north-south orientation optimizes solar heating and natural lighting