Project Statistics
Location: Concord, New Hampshire
Type: Community center, daycare, preschool
Size: 8,900 sq. ft.
ICF Use: 22,800 sq. ft.
Cost: $4.5 million
Total Construction: 56 weeks
ICF Installation Time: 28 working days
Construction Team
Owner/Developer: Boys and Girls Club of Central NH
General Contractor: Milestone Construction
ICF Installer: Key Industries LLC
Form Distributor: Atlantic Builders Supply Northeast
Architect: Team Engineering
ICF System: Nudura
Fast Facts
- 20-foot-high free-spanning walls
- Both conventional CIP and ICF foundations
- Perimeter steel columns set into the ICF Walls
- 150+ foot-long straight wall with no jogs or corners