Project Statistics 


Location: Cabin John, Maryland
Type: Home & educational museum
Size: 5,200 sq. ft. 
ICF Use: 3,120 sq. ft. 
Cost: $1,500,000
Total Construction: 24 weeks
ICF Installation Time: 10 days

Construction Team 


Owner/Developer: Green Casa Maryland
General Contractor: Green Casa Maryland
ICF Installer: Green Casa Maryland
Form Distributor: BuildBlock
ICF System: BuildBlock

Fast Facts 


Built as a test case for energy-efficient construction materials
Walk-through museum to teach the benefits of ICF
Incorporates a wide variety of energy-efficient materials 
ICFs were the only structural material that could achieve the goals
LEED-certified and Net Zero home
Thousands learned about ICFs from this one project