2022 MultiFamily
2nd Runner-Up

Project Statistics 


Location: Calgary, Alberta, Canada
Type: Multifamily affordable housing
Size: 110,000 sq. ft. 
ICF Use: 50,000 sq. ft. 
Cost: $37,000,000
Total Construction: 64 weeks
ICF Installation Time: 5 days per floor, 18 floors

 

Construction Team 


Owner/Developer: Kanas Corp.
General Contractor: Kanas Corp.
ICF Installer: Kanas Corp.
Architects: Casola Koppe Architects
Engineer: Eco Engineering
ICF System: SuperForm

Fast Facts 


  • 18-story highrise
  • 110,000 sq. ft. with 135 residential units
  • Co-generation and photovoltaic solar arrays
  • Built to green platinum standards
  • Uses 1/5th the energy of a traditional highrise
  • Multilevel parkade