2025 Specialty Application
Winner

Project Statistics


Location: Comox, British Columbia
Type: Caregiver addition
Size: 970 sq ft.
ICF Use: 6,290 sq. ft.
Cost: $400,000
Total Construction: 104 weeks
ICF Installation Time: 122 days

Construction Team


Owner/Developer: Ken McDonald
General Contractor: Ken McDonald
ICF Installer: Ken McDonald
Form Distributor: Cedar Grove Building Products
Architect: Jennifer Charles Design
ICF System: Quad-Lock, Quad-Deck

Fast Facts


  • Integrated into current home on 22-foot hill
  • Many acute- and obtuse-angled corners
  • Minimal site footprint, and is Net Zero
  • Meets BC Building CODE Step 5 standards, seismic standards
  • Custom Quad-Deck ICF with integrated in-floor radiant tubing
  • Multigenerational design with wheelchair access, elevator
  • 1,400 sq.ft. rooftop deck