2026 Heavy Commercial
2nd Runner-Up & People’s Choice
Project Statistics
Location: Natick, Massachusetts
Type: Mixed use, residential
Size: 20,000 sq. ft.
ICF Use: 36,290 sq. ft.
Cost: $11 million
Total Construction: 78 weeks
ICF Installation Time: 70 days
Construction Team
Owner/Developer: Stonegate Group LLC
General Contractor: PointsNorth Construction Management
ICF Installer: Key Industries LLC
Form Distributor: Atlantic Builders Supply Northeast
Architect: Main Street Architects
ICF System: Nudura by Tremco CPG
Fast Facts
-
Originally designed with metal framing; switched to ICFs after steel structure was erected
-
ICFs reduce noise from nearby train tracks
-
Using ICF saved 12 weeks in schedule, 10% on building envelope costs
-
Featured in the New England Real Estate Journal
-
ICFs enabled winter construction