2026 Education
2nd Runner-Up
Project Statistics
Location: Ashtabula, Ohio
Type: Private school
Size: 22,000 sq. ft.
ICF Use: 16,200 sq. ft.
Cost: $6 million
Total Construction: 61 weeks
ICF Installation Time: 20 days
Construction Team
Owner/Developer: Saint John School
General Contractor: Housel Construction
ICF Installer: Olympic Construction
Form Distributor: Nudura by Tremco CPG
Architect: Onyx Creative Inc.
ICF System: Nudura by Tremco CPG
Fast Facts
-
Small private K-12 Catholic school
-
Funded through a capital campaign and charitable contributions
-
No state or local funding sources were used on this project
-
Saved 30 days construction time by using ICFs
-
ICFs allowed for winter construction