vote BELOW for the ICF Builder
People’s Choice Awards between
DECEMBER 13, 2024 & JANUARY 3, 2025

Steps to submitting your vote!

• Watch the Project Videos Below
• Scroll to the bottom and VOTE!

Specialty Applications

McDonald Project

Location: Comox, British Columbia
Type: Caregiver addition
Size: 970 sq ft.
ICF Use: 6,290 sq. ft.
Cost: $400,000
Total Construction: 104 weeks
ICF Installation Time: 122 days

Laurel Safe Room/Shed

Location: Laurel, Mississippi
Type: Safe room/shed
Size: 590 sq. ft.
ICF Use: 654 sq. ft.
Cost: $35,000
Total Construction: 3 weeks
ICF Installation Time: 3 days

Bluffside Party Pad

Location: White Salmon, Washington
Type: Garage, gathering space
Size: 950 sq. ft.
ICF Use: 3,500 sq. ft.
Cost: $550,000
Total Construction: 11 months
ICF Installation Time: 5 days

 

Pools

Ozark Mountain Vista Pool

Location: Bentonville, Arkansas
Type: Pool
Size: 800 sq. ft.
ICF Use: 1,400 sq. ft.
Cost: $350,000
Total Construction: 16 weeks
ICF Installation Time: 10 days

 

West End Oasis

Location: St. John’s, Newfoundland and Labrador, Canada
Type: Pool
Size: 612 sq. ft.
ICF Use: 663 sq. ft.
Cost: $336,000
Total Construction: 49 weeks
ICF Installation Time: 28 days

Scuba Recreation Park

Location: Terrell, Texas
Type: Scuba training pool
Size: 754 sq. ft.
ICF Use: 1,858 sq. ft.
Total Construction: 40 days
ICF Installation Time: 17 days

 

Small Residential

Mt. Washington Chalet

Location: British Columbia, Canada
Type: Residence
Size: 2,055 sq. ft.
ICF Use: 3,550 sq. ft.
Cost: $925,000
Total Construction: 208 weeks
ICF Installation Time: 150 days

 

Hobbit Airbnb

Location: Crestone, Colorado
Type: Themed Airbnb
Size: 1,800 sq. ft.
ICF Use: 2,540 sq. ft.
Cost: $800,000
Total Construction: 48 weeks
ICF Installation Time: 14 days

Rockhaven Parade Home

Location: Nampa, Idaho
Type: Residence
Size: 2,206 sq. ft.
ICF Use: 1,175 sq. ft.
Cost: $477,000
Total Construction: 16 weeks
ICF Installation Time: 6 days

LARGE Residential

Iyer Residence

Location: Santa Rosa, California
Type: Residence
Size: 3,717 sq. ft.
ICF Use: 23,548 sq. ft.
Cost: $3 million
Total Construction: 168 weeks
ICF Installation Time: 520 days

 

Pegasus’s Airpark

Location: Queen Creek, Arizona
Type: Residence with aircraft hangar
Size: 5,060 sq. ft.
ICF Use: 13,174 sq. ft.
Cost: $2,047,425.89
Total Construction: 156 weeks
ICF Installation Time: 35 days

Bertelson Residence

Location: Winterset, Iowa
Type: Residence
Size: 5,168 sq. ft.
ICF Use: 13,976 sq. ft.
Cost: $3 million
Total Construction: 160 weeks
ICF Installation Time: 60 days

 

UnLimited Residential

Providence

Location: Central Texas
Type: Residence
Size: 6,800 sq. ft.
ICF Use: 12,630 sq. ft.
Cost: $1.5 million
Total Construction: 136 weeks
ICF Installation Time: 44 days

 

Jackson Residence

Location: Brownsboro, Alabama
Type: Residence
Size: 8,999 sq ft.
ICF Use: 16,720 sq. ft.
Cost: $4.8 million
Total Construction: 150 weeks
ICF Installation Time: 80 days

Altamura Residence

Location: Santa Rosa, California
Type: Residential
Size: 7,975 sq. ft.
ICF Use: 36,231 sq. ft.
Cost: $3.5 million
Total Construction: 156 weeks
ICF Installation Time: 380 days

 

Light Commercial

Alachua County Tax Collector’s Office

Location: Gainesville, Florida
Type: Public office
Size: 16,624 sq. ft.
ICF Use: 6,696 sq. ft.
Cost: $3.9 million
Total Construction: 50 weeks
ICF Installation Time: 20 days

 

Sherwin-Williams Oklahoma City Retail Project

Location: Oklahoma City, Oklahoma
Type: Retail, showroom
Size: 4,615 sq. ft.
ICF Use: 5,040 sq. ft.
Cost: $1.2 million
Total Construction: 24 weeks
ICF Installation Time: 21 days

Bristol Public Safety Building

Location: Bristol, New Hampshire
Type: Public safety building
Size: 19,808 sq. ft.
ICF Use: 11,100 sq. ft.
Total Construction: 57 weeks
ICF Installation Time: 68 days

 

MultiFamily Low-Rise

Linear Heights

Location: San Antonio, Texas
Type: Multifamily building
Size: 898 sq. ft. per unit, 3 units
ICF Use: 12,939 sq. ft.
Cost: $1,048,000
Total Construction: 68 weeks
ICF Installation Time: 12 weeks

 

Cottonwood Village

Location: Powell, Wyoming
Type: Subdivision
Size: 2,200 sq. ft. per home
ICF Use: 30,000 sq. ft.
ICF Installation Time: 4 days per home

Hooper Avenue Apartments

Location: Fairbanks, Alaska
Type: Apartments
Size: 8,223 sq. ft.
ICF Use: 19,345 sq. ft.
Cost: $1.5 million
Total Construction: 48 weeks
ICF Installation Time: 22 days

 

MultiFamily

The Alexander Condominium

Location: Huntsville, Ontario
Type: Condominium
Size: 50,355 sq. ft.
ICF Use: 45,045 sq. ft.
Cost: $13,891,797.30
Total Construction: 92 weeks
ICF Installation Time: 170 days

 

Royal Canadian Legion Branch 25

Location: Sault Ste Marie, Ontario
Type: Mixed-use residential
Size: 154,780 sq. ft.
ICF Use: 94,400 sq. ft.
Cost: $32.7 million
Total Construction: 72 weeks
ICF Installation Time: 184 days

The Alexander Residence

Location: Gravenhurst, Ontario
Type: Retirement home
Size: 77,223.20 sq. ft.
ICF Use: 36,244 sq. ft.
Cost: $19,496,526
Total Construction: 106 weeks
ICF Installation Time: 221 days

 

Heavy Commercial

White Shield Old Scouts Veterans Memorial Center

Location: White Shield, North Dakota
Type: Tribal gathering center
Size: 10,533 sq. ft.
ICF Use: 10,900 sq. ft.
Cost: $11,000,000
Total Construction: 56 weeks
ICF Installation Time: 25 days

 

Moses Lake Washington Temple

Location: Moses Lake, Washington
Type: Temple
Size: 28,933 sq. ft.
ICF Use: 21,320 sq. ft.
Cost: $7,609,978
Total Construction: 90 weeks
ICF Installation Time: 150 days

Huron Poultry Barn

Location: Brownlee, Saskatchewan
Type: Poultry barn
Size: 37,000 sq. ft.
ICF Use: 19,500 sq. ft.
Total Construction: 50 weeks
ICF Installation Time: 40 days

 

Education

Gateway Church

Location: Manitoba, Canada
Type: Church and school
Size: 82,100 sq. ft.
ICF Use: 77,039 sq. ft.
Cost: $13.9 million
Total Construction: 98 weeks
ICF Installation Time: 115 days

 

Liberty High School (Storm Shelter)

Location: Lubbock, Texas
Type: School facility
Size: 36,000 sq. ft.
ICF Use: 41,900 sq. ft.
Cost: $20 million
Total Construction: 117 weeks
ICF Installation Time: 168 days

Penacook Community Center Boys & Girls Club of Central NH

Location: Concord, New Hampshire
Type: Community center, daycare, preschool
Size: 8,900 sq. ft.
ICF Use: 22,800 sq. ft.
Cost: $4.5 million
Total Construction: 56 weeks
ICF Installation Time: 28 working days

 

VOTE NOW

Enter your name and email address below to register to vote

(Only 1 entry per email address will be counted)

People's Choice Awards

Step 1 of 11 - Register to Vote

ICF Builder Awards Program Preview

2025 ICF Builder Awards Event RSVP

Day(s)

:

Hour(s)

:

Minute(s)

:

Second(s)

Join us at World of Concrete January 22, 2025 @ 5:00 p.m.